Allotment
Procedure >> |
UPSIDC has categorised the areas
into Very Fast, Fast and Slow moving
depending on the market demand, industrialisation
and infrastructure position. Allotment
procedure varies with category. Categorisation
of Industrial areas be seen before appreciating
the allotment procedure. |
| Very Fast/Fast Moving Areas |
Slow Moving Areas |
| Advertisements periodically in national newspaper
calling applications |
Applications can be obtained and deposited in
Regional offices anytime |
| Interview of the applicants to check their genuinity
and interest |
Allotments on first come first served basis |
|
Application
Procedure
Application form and other documents
should be submitted as per details below:
- Duly filled application form obtainable
from Regional office to be submitted
in duplicate with the concerned regional
office.
- Project report duly signed to be
submitted in duplicate
- Rough layout plan in duplicate
- Detail of applicant’s constitution
e.g. partnership deed, Article/ Memorandum
of association, list of shareholder
& director.
- Bank Draft for Earnest and Processing
money as per details given in the
application form, in name of UPSIDC
Ltd payable at place of deposit of
application.
|
Terms Of Allotment
Terms of allotment vary with the category
of Industrial area. |
| Very Fast/Fast Moving Areas |
Slow Moving Areas |
| 25% of total amount to be deposited in 30 days
|
10% of total amount to be deposited in 30 days |
| Balance 75% in 10 equal 6 monthly installments
along-with interest on balance
amount |
After 2 years moratorium, balance 90%in 8 equal 6 monthly installments
along-with interest on balance
amount |
| Possession after execution of Lease Deed to be executed within
3 months |
Possession after execution of Lease Deed to be executed within
3 months |
| Unit to be brought under production in 2 years covering 30%
area |
Unit to be brought under production in 2 years covering 30%
area |
|